There are many joints in sheet

metal. Some joints are called

self-secured joints. This is

where we use the job’s own

metal. Examples are Groove

joint, Slip joint and Peined

joint. They all have different

amounts of metal involved in

their assembly. It is important

to allow for these joints when

marking out a pattern.

Figure I, shows the elevation.

Figure II, development of the

lower socket, seam on the

inside.

Figure III, development of the

lower socket, seam on the

outside.

After determining the outline

of the elevation of figure I as

mentioned in section 1 above,

draw the semi-circle at point d,

divide into six equal parts and

through points 2 and 6 draw

the so called generating lines

parallel to the middle line. The

joint line of the two pipe

sockets is a straight line. The

development is obtained as

described in table 1 by laying

off the line segment 1 to 2 (or

the arc in figure1) 12 times on

a base line, drawing the

perpendiculars at points a to g,

and on these points laying off

the respective line segments

aA, bB, etc. of figure I. As

mentioned above, it is very

important when stepping of

the 12 arc lengths or divisions

not to accumulate an error

which would make the

circumference longer or

shorter than required.

Note: The pipe can also be

developed by calculating it’s

circumference (diameter x π)

and then by dividing the

circumference in half,

quarters, and then each quarter

into three equal and accurate

divisions with no

accumulation or error.

2.2 Development of an

Offset

Figure I: Elevation.

Page 33

Figure II: Development of

socket A.

Figure III: Development of

socket B.

Figure IV: Development of

socket C.

First determine the outline of

the elevation of the offset in

figure I and take care to give

the three segments or pipes

the correct diameter. Then

draw the semicircle with the

centre at point 4, divide it into

six equal parts and through

points b, c, e, and f draw the

so-called generating lines

parallel to the middle lines of

the three segments. The

development of the two

sockets A and C is described

in the previous tables above.

For the development of the

middle socket B draw the

auxiliary line 1 to 7

perpendicular to the middle

line in figure 1. This auxiliary

line is constructed at a random

point on the centreline 11 to

18. The generating line yields

points 1 to 7.

For the development of figure

III determine the base line

with points 1 to 7 as usual.

Draw the perpendiculars at

these points and on these lines

lay off the various lengths of

the lines above and below the

base line. All these lines

should be the same length.