2.6 Efficient Drawing Layout and Sequencing
Page 36
equal parts and from this find
points 2 to 6 and draw the
perpendiculars to the base line.
Lay off 600mm from point s
to point p, which may be
inside or outside the
semicircle, and draw the
perpendicular at p and lay off
the respective value of x found
in the chart and place at point
Q.
From point Q draw the
connecting line S intersecting
the perpendiculars of the
semicircle at points A to G.
The line segments aA, bB, etc.
are the parts needed for the
development in figure 2.
In figure 2 the allowances for
the male/female seam and for
the overlap are already added.
The allowances for the beaded
pieces in the elevation can be
added at the base line or better
still at the mitre lines as done
here.
2.6 Efficient Drawing
Layout and Sequencing
of Layouts
Today it is customary in the
insulating industry to develop
fittings according to section
2.5 above. When cutting the
plates to size, metal waste and
cutting can be reduced by
alternatively laying the various
segments one under the other.
It is very important to nest the
various patterns together to
maximise economy of
materials. Also the connection
of the individual segments is
almost only made with a
beaded piece and counter
piece as shown under the arc
in figure 1. The average
allowance for the beaded
pieces is 8 mm, in other words
4 mm for half the
development. For smaller
pipes and small beaded pieces
3mm is enough of an
allowance.
Refer to Module 1 – Unit 9 –
Metal cladding assembly
work.
Refer to Module 1 – unit 5 –
General allowances for
insulation and
cladding.
Refer to module 1 – unit 4 –
Notching, folding and
joining.